Analysis How Replacing GE F404 Engine on Tejas Mk1A Fighters Could Take 5 to 7 Years of Airframe Redesign and Testing

How Replacing GE F404 Engine on Tejas Mk1A Fighters Could Take 5 to 7 Years of Airframe Redesign and Testing


With the Indian Air Force facing significant delays in receiving its Light Combat Aircraft (LCA) Tejas Mk1A fleet due to the slow delivery of General Electric (GE) F404-IN20 engines from the United States, public debate has naturally shifted toward finding alternative powerplants.

However, according to an experienced former engineer from Hindustan Aeronautics Limited (HAL), swapping the current GE engine for another option is far from a quick fix.

Speaking anonymously, the aerospace expert revealed that integrating a different engine would demand extensive airframe redesigns, essentially resulting in the creation of a completely new variant of the fighter jet.

In modern aerospace engineering, an aircraft's engine is much more than just a source of forward thrust; it acts as the core of the entire platform, dictating its overall shape, capabilities, and safety.

For an advanced fly-by-wire fighter like the Tejas Mk1A, the chosen powerplant directly influences the aircraft's weight distribution, structural stress points, air intake requirements, heat management, and the complex software that keeps the jet flying smoothly.

The former HAL official clarified that the Tejas Mk1A’s physical structure was custom-tailored specifically around the GE F404-IN20 engine. Choosing a different engine would mean overhauling several vital aerodynamic and internal systems.

For instance, the jet's air intakes are shaped to capture the exact volume and pressure of air that the GE engine requires.

An alternative engine, which would naturally pull in air at different rates, would force engineers to completely redraw and manufacture new intake channels to prevent critical issues like airflow disruption or engine stalling.

Beyond aerodynamics, the physical way the engine connects to the aircraft would need a drastic redesign. The internal structural mounts must be rebuilt to handle the specific vibrations, weight, and force generated by a new engine.

Furthermore, the electronic brain of the engine—the Full Authority Digital Engine Control (FADEC)—would require a complete software rewrite to guarantee it can communicate perfectly with the Tejas’s main mission computers and digital flight controls.

The rear section of the fighter would also face major structural changes. Because different jet engines have varying nozzle sizes, exhaust heat levels, and thrust outputs, the rear fuselage would need to be re-engineered with new heat shields and strengthened structural frames.

Even the aircraft's internal fuel delivery lines and cooling systems would have to be adjusted to manage the unique temperature and operational demands of a different engine.

Such a massive engineering overhaul would trigger a long and demanding certification journey.

The veteran engineer estimated that just the initial computer-based design and simulation phase—analyzing aerodynamics, structural strength, and heat distribution—could take up to 18 months.

This would be followed by another year and a half of rigorous ground tests to ensure the new engine does not cause dangerous vibrations or compatibility issues within the airframe.

Following these ground checks, the most time-intensive phase would begin: actual flight testing.

A re-engined Tejas would need to complete anywhere from 300 to 500 hours in the air under extreme conditions, evaluating everything from high-altitude performance to high-speed turns and weapons carriage.

In total, achieving Initial Operational Clearance (IOC) for this heavily modified jet would take an estimated five to seven years.

Testing would also stretch far beyond just making sure the engine works. Engineers would need to verify that a shift in the aircraft's centre of gravity does not make the jet structurally unstable during combat manoeuvres.

Crucially, because a new engine changes the way air flows over the wings and fuselage, every single weapon carried by the Tejas would have to be tested all over again.

Missiles like the Astra, precision bombs, and upcoming weapons such as the BrahMos-NG would need fresh safety certifications to ensure they can be released safely without colliding with the aircraft.

The former HAL professional stressed that public discussions often ignore these harsh engineering realities when suggesting quick replacements.

For example, while the French Safran M88 is a highly capable engine that successfully powers the Rafale fighter, placing it inside the Tejas would still require massive modifications to the aircraft's body due to its different dimensions and technical architecture.

Similarly, while India's homegrown Kaveri engine remains a critical piece of the nation's long-term goal for defence self-reliance, it is currently focused on a separate development path aimed at powering unmanned drones, such as the Ghatak UCAV, with certification milestones targeted around 2026.

The Kaveri has not yet reached the strict reliability metrics and operational standards required for a frontline manned fighter jet, making it an unviable immediate replacement.

Ultimately, navigating the current supply chain hurdles with GE, rather than redesigning the aircraft, remains the only practical path forward for the current Tejas Mk1A programme.
 
what is stopping them for the simulations to be done now..you can do the simulations ..dont add the time line of simulation..as it can be done without engine being running ..only you need to set the boundary condition.need to ask that guy how much reall experience he have on product development..
 
There are videos on YouTube claiming that Saab will re-engine the Gripen with the Eurojet EJ200, or versions of it. Saab had denied such claims for the exact same reasons as in this article. At the cost of doing such a project, it would be more cost-effective to develop a new fighter.
The same applies to the Tejas Mk1A. HAL has the TEDBF, the Tejas Mk2 and possibly ORCA in the works. They already have its hands full. No need for them to be distracted by a project that may further delay deliveries of existing aircraft, and projects.
 
Bad idea, IAF shld stop with further orders and even engine delay let it finish those two order they were made. 2nd order final delivery deadline is 2034.

If any new engine integrate in Tejas Mk1 variant then it shld be home developed engine only.

Even that engine developed and certified , no need more than 1 squadron . Here if we belive Kaveri with new after burner integrated and achieved 84 to 90kN thrust too. Then order 1 squadron and keep with IAF and focus that $hit Tejas Mk1a with upgraded Kaveri engine for exports sales only ,if any nation willing to buy . Otherwise waste of money and time
 
If they could, they would have come forward. Jet engine technology is extremely complex, and only 5-6 companies globally possess this technology.
 
HAL is a joke. They have failed to meet the initial requirements and the targets have never been met.
 
30 brand-new Tejas aircraft are ready without engines, which is a fiasco not only for Indian defence planners but also for DRDO's past and present top brass, who should be held accountable for such lousy planning, as after 40 years India could not produce jet engines, nor did those planners have a plan B. That's what this write-up states. This is as good as a betrayal of the country, which is a punishable offence. Heads should roll for a better future for the nation. The blame game won't yield results when one doesn't have an action plan to follow or review.
India should have DRDO/HAL-like defence organisations in responsible hands and NOT be controlled by babu-type scientists.
 
It is better to do the engine swapping now than at a later date. GE isn't supplying and won't supply you engine be it 404 or 414. They will only make promises like HAL do. It is advisable to scrape the second order of MK IA and put resources and time to redesign MK II structure to accommodate some other engine in place of 414. Give a boost to Kaveri project and set up our own test bed for the engine instead sending engine to other countries. US won't allow you to manufacture your own jet. Writting is on the wall but our planners are unable to see it. India needs a independent strategic think tank of experts free from any interference to advise the government on the defence matters. Jai Hind Jai Bharat.
 
There are videos on YouTube claiming that Saab will re-engine the Gripen with the Eurojet EJ200, or versions of it. Saab had denied such claims for the exact same reasons as in this article. At the cost of doing such a project, it would be more cost-effective to develop a new fighter.
The same applies to the Tejas Mk1A. HAL has the TEDBF, the Tejas Mk2 and possibly ORCA in the works. They already have its hands full. No need for them to be distracted by a project that may further delay deliveries of existing aircraft, and projects.
There was speculation that Gripen E might be offered to Canada with EJ200. SAAB publicly quashed the rumour, saying it would not be offering Gripen E with EJ200.
 

Forum statistics

Threads
7,519
Messages
66,855
Members
5,511
Latest member
Parag
Back
Top